A Legacy of Innovation

Chiripal Poly Films embarked on its journey in August 2009, with a vision to become a leading player in the flexible packaging industry. In January 2012, this vision took shape as the company commenced production at its state-of-the-art facility in Ahmedabad, India. Equipped with cutting-edge German technology, the initial production line focused on manufacturing high-quality BOPP films. Today, the company has achieved 3 manufacturing locations, 8 film lines, PET resin plants, and a diversified product portfolio.

Milestones and Growth Path

BOPP Solutions

2012

BOPP line 1

Ahmedabad Plant

  • 39k TPA production capacity
  • 3-layer films
BOPP Solutions

2013

BOPP line 2

  • 39k TPA production capacity
  • 5-layer films
BOPP Solutions

2015

BOPET line 1

  • 38k TPA production capacity
  • 3-layer films
BOPP Solutions

2017

PET resin plant

Backward Integration

  • 220k TPA production capacity
  • Bottle | Films | Textile
BOPP Solutions

2019

COATING line 1

  • 4.5k TPA production capacity
  • SSP expansion
  • 146k TPA
BOPP Solutions

2021

BOPP line 3

Hyderabad Plant

  • 55k TPA production capacity
  • 10.4 mts width
BOPP Solutions

2022

BOPET line 2

  • 42k TPA production capacity
BOPP Solutions

2023

CPP line

  • 14k TPA production capacity

CPP line

  • 8k TPA production capacity
BOPP Solutions

2025

  • Aluminium foil 25k TPA
  • BOPP line 4 61 TPA
  • rPET line 36 TPA

Milestones and growth path

2012

BOPP line 1

Ahmedabad Plant

  • 39k TPA production capicity
  • 3-layer films

2015

BOPET line 1

  • 38k TPA production capicity
  • 3-layer films

2019

COATING line 1

  • 4,5k TPA production capicity
  • SSP expansion
  • 146k TPA

2022

BOPET line 2

  • 42k TPA production capicity

2025

  • Aluminium foil 25k TPA
  • BOPP line 4 61 TPA
  • rPET line 36 TPA

2013

BOPP line 2

  • 39k TPA production capicity
  • 5-layer films

2017

PET resin plant

Backward Integration

  • 220k TPA production capicity
  • bottle | films | textile

2021

BOPP line 3

Hyderabad Plant

  • 55k TPA production capicity
  • 10,4 mts width

2023

CPP line

  • 14k TPA production capicity

Coating line 2

  • 8k TPA production capicity